Randenigala
Reservoir /Dam
The Randenigala Project, the fourth major multi-purpose
project and the largest reservoir under the Accelerated Mahaweli
Development Programme. Randenigala project is located about 26 km.
below the Victoria Head works and 6 km. upstream of Minipe anicut
from where the main Right Bank and Left Bank canals will divert the
Mahaweli waters for irrigation. It is also the reservoir with the
largest storage capacity having gross storage of 860 million cubic
metres (697,000 acre ft.) at full supply level. The project is
expected to generate about 525 GWh of electrical energy which
amounts to 20% of the island’s present demand. It will serve as the
most important base reservoir for water management in System ‘A’,
‘B’ and ‘C’.
Project Features
The project
chiefly consists of the construction of a 94 m.(308 ft) high, 485
m.(1590 ft.) long Rock-fill dam across Mahaweli, created a reservoir
of 860 million cu.m. (697,000 ac.ft.). The Power House on the Left
bank immediately downstream of the dam has an installed capacity of
126 MW. A steel lined tunnel 6.2 m. dieameter, 270 m. long, convey
water to the Power House to run the turbines. The triple gated chute
spillway is 48 M. wide, about 232m. long and is capable of
discharging the probable maximum flood of 8085 cumecs.
Finances
The total cost
of these Headworks is approximately Rs. 4898 million of which Rs.
1207 million is the local component and Dautsche Marks 410 million
is the foreign component in 1985. The Federal Republic of Germany
first granted a loan for a value of about DM 240 million (Rs.2160
million) and has extended a loan to the value of DM 400 million on
favourable terms for Randenigala Project. (Rs. 2,528,455 as at the
balance sheet 2004) (Rs.’000)
Consultancy
services
The
consultants for the Project is Joint Venture Randenigala (JVR), a
firms, Salzgitter Consult GmbH, Agrar-Und Hydro-technik GmbH and
Electrowatt Engineering Services Ltd along with the Engineers of the
Central Engineering Consultancy Bureau. (CECB)
Construction work commenced in 1982. The reservoir was impounded in
March 1986, construction of the rockfill dam, spillway and power
station were completed in 1986, according to schedule. The two
turbine generator units were commissioned in August and September
1986.
Scope
A dam at
Randenigala site with power station and other appurtenant structures
together with a lower dam at Rantembe (immediately below the
confluence of the Uma Oya with the Mahaweli ganga), and power
station.
The Main
Physical Components of the Project
The average
annual rainfall within the Randenigala Project area ranges from
1250mm to 3000 mm.
The
Randenigala Project basic parameters :
Dam type
Rockfill with Claycore
Recervoir
(As at
Projects & Programme 1988)
Catchment area - 2,330 sqKm
Gross storage capacity - 861 MCM
Live storage capacity - 558 MCM
Surface at retention level - 1350Ha
Main Dam
Dam Length -
485 m
Dam Height - 94.0 m
Crest elevation - 239.0 m MSL
Crest width - 10 m
Maximum base width - 303 m
Spill way
Maximum
capacity - 8,100 m 3/ s
Number of gates - 3
Type of gates - Taintor
Hight of gate - 15.26 m
Width of gates - 16.70 m
Length of chute spillway - 232 m
Tunnel Bottom
& Irrigation Outlet
Length - 5646
metres
Diameter of tunnel
Inside concrete lining - 6.2 metres
Depth of surge chamber - 116 meters
Generators & Turbines
Number of
turbine & Generator - 2
Type of turbines - Francis
Setting of turbines - 148.50 m MSL
Installed capacity - 2 x 63 MW
Annual estimated energy
Generation firm - 428 GWh (one million units)
Secondary - 100 GWh |